| Address | 7777 Edinger Ave Unit |
| APN | 142-073-29 |
| Permit Number | C2017007180 |
| Permit Type | Combination |
| Status | Pending |
| Applied Date | Oct 30, 2017 |
| Issued Date | |
| Finale Date | |
| Description (12) NEW TESLA SUPERCHARGERS W/ POSTS AT (E) PARKING STRUCTURE STALLS ***BELLA TERRA*** ***2/16/21 MW - SUP: REVISED PLANS - (6) Tesla charging cabinets, (1) switchgear with utility meter, (1) utility transformer, (1) utility PME switch, (1) utility capacitor, (1) electrical distribution panel. Install associated concrete pads for exterior equipment and metal bases for interior equipment.**** | |
| Department | Building |
| Last Sumitted Date | Feb 16, 2021 |
| Date Complete | Feb 16, 2021 |
| Status | Approved/Waived |
| Reviewer | Lee, Eddie |
| [email protected] | |
| Status Comments [Approved] 02/16/2021 by leeed] | |
| Department | Building |
| Last Sumitted Date | Feb 16, 2021 |
| Date Complete | Feb 16, 2021 |
| Status | Approved/Waived |
| Reviewer | Lee, Eddie |
| [email protected] | |
| Status Comments [Approved] 02/16/2021 by leeed] | |
| Department | Electrical |
| Last Sumitted Date | Feb 16, 2021 |
| Date Complete | Feb 23, 2021 |
| Status | Correction Required |
| Reviewer | Moreno, David |
| [email protected] | |
| Status Comments | |
| Department | Electrical |
| Last Sumitted Date | Feb 16, 2021 |
| Date Complete | Feb 23, 2021 |
| Status | Correction Required |
| Reviewer | Moreno, David |
| [email protected] | |
| Status Comments 2/16/21 MW - REV01 ON EPROCESS | |
| Department | Fire |
| Last Sumitted Date | Feb 16, 2021 |
| Date Complete | Feb 17, 2021 |
| Status | Approved/Waived |
| Reviewer | Eros, Steve |
| [email protected] | |
| Status Comments 11/29/2017 SE REVIEWED AND APPROVED THE REVISED PLANS 11/06/17 SE REVIEWED AND APPROVED THE TESLA CHARGING STATION. [Approved] 11/06/2017 by eross] [Approved] 11/29/2017 by eross] | |
| Department | Fire |
| Last Sumitted Date | Feb 16, 2021 |
| Date Complete | Feb 17, 2021 |
| Status | Approved/Waived |
| Reviewer | Eros, Steve |
| [email protected] | |
| Status Comments 2/19/21 SE APPROVED THE REVISED PLANS. [Approved] 02/18/2021 by eross] | |
| Department | Planning |
| Last Sumitted Date | Feb 16, 2021 |
| Date Complete | Feb 24, 2021 |
| Status | Approved/Waived |
| Reviewer | Kelley, Jason |
| [email protected] | |
| Status Comments 04/12/18: JK- plans OK- ready for final signatures 11/30/17: CW - plans submitted 11/17/17 stamped, signed, and approved for JK 11/27/17: JK - plans OK - ready for final signatures 11/06/17: JK - plans OK - ready for final signatures [Approved] 11/30/2017 by planzone1] | |
| Department | Planning |
| Last Sumitted Date | Feb 16, 2021 |
| Date Complete | Feb 24, 2021 |
| Status | Approved/Waived |
| Reviewer | Kelley, Jason |
| [email protected] | |
| Status Comments [Approved] 02/24/2021 by kelleyj] | |
If you don't have an email address or if the "Review Information" area doesn't contain the reviewer's email address, please contact us by phone.
Building & Safety: (714) 536-5241
Planning: (714) 536-5271
Fire: (714) 536-5411
Public Works: (714)-536-5431